Day 143
Here are the bathroom fittings all in place. the guys have rendered the wall roughly so that it's ready for the tiles. This is the sink...


Day 142
This is the view from the roof top of my room. Today they put in the 'gutters' or spouts. i don't know what to call them or what to say....


Day 141:
This is a space cleared by the house. I forget why i took this picture. I wanted to do some planning but now I forget. I took a picture...


Day 140: Inspection
​A lady came to inspect the workplace. The guys were interviewed and they gave her a tour of the place. With the amount of laughing I...


Day 139: Painting
The big flattener tractor came and drove around the entire place to prepare for the terraces. ​ ​​ ​​ ​After he flattened the land,they...


Day 138
Fixing the holes of the electric outlets Sandra and Yeray came to visit the house and meet the guys laying the fibreglass and painting...


Day 137
​ ​The guys swept the floors so that they could prepare for the last layer of cement. This is the laundry room/pantry dance studio...


Day 136: rolling out the fibreglass
​ ​So this is how they waterproof the roof top. Once the final layer of cement is set, they roll out the fibreglass. to stick it to the...


Day 135: Painting and laying fiberglass
The guys laid the fibreglass waterproofing and started painting the rooftop today. Photo credits to Guzman :) he's my photographer today...


Day 134: Pouring the last layer of Cement
​They poured the top layer of cement over the guest room, guest bathroom and the Master bedroom and bathroom. Tomorrow, after the cement...