Day 8: Finishing the levelling of the ground
They finished leveling the ground. They had to bring in more gravel/soil to raise the level of the ground. This is what they used to fill...


End of Day 7
Just so you know, the construction guys don't work on the weekends. But I wanted to see how much the guy had finished Friday afternoon....


Day 7: Measuring the ground level
Today I saw the tractor at work (instead of a camera, I had a rake in my hand and couldn't take a video). The man was moving all the...


Day 6: Levelling the ground
All the rocks sticking out of the ground were removed (some moved to the side) and others used to fill the dips in the ground. If you...


Day 5: Digging machine came back
The digging machine came back but I didn't see any progress. I did notice they brought the drill. It must be for removing the rocks that...


Day 4: I didn't notice any change :(
I'm not quite sure what happened today. I went to the site and it was exactly as it was on day 3. I wonder if there was an issue with...