Day 104 pot pourri part 2

  • Writer: Eva Hu
    Eva Hu
  • Jun 30, 2016
  • 2 min read

There was a lot going on today. Let's start with the rendering in the inner terrace.

Look at what they used instead of scaffolding! That must have been what the wooden structure in the master bathroom was for. To hold the piece of wood out on the other side.

I just saw this and thought it looked nice.

I was meant to help but I ended up going to Tamaragua to fix some walls in the garden. The guys at the house put a bucket of cement in my trunk and I rendered on my own. The first time i did it, it was ok. but the second trip. I did a crappy job. The guys said they should have come with me. but it's too late. :( Next time...

And since I was figuring out tamaragua, I didn't have a chance to help out at the house today.

Let's go back and see what else they did. This is the view from the master bath. they put in a wooden frame. I'm not quite sure why.I thought window frames that open to outside are aluminium...

Here's the frame for the main bathroom.

They are also putting up blocks. I don't know why they didn't finish the blocks together in one day.

The electrician came today and did the electricity in the house section. There are tubs sticking out everywhere. it's like the scene of an alien movie.

There are tubes that are for grounding. Luis explained that the electricity is wired to something so you can't get electrocuted...I don't understand but I will.

You can see the one tube sticking out of the ground. This is for the electric outlet on the island in the kitchen.

Each plug needs it's own individual tubing. That's why it looks so crazy!