Day 93: moving onto the outside
- Eva Hu
- Jun 15, 2016
- 2 min read

The guys started rendering on the outside. They are almost finished the stairs. I thought they would actually finish making the stairs before they rendered it...but I guess they know what they are doing. Maybe they are waiting for all the other parts of the house that need concrete so they dump the big load of concrete all at once. I don't know. I'm just guessing.
Dance studio...check.


under the stairwell.

workshop...check.

behind door number 3. the storage area. the area over the wall will be storage space because the bathroom ceiling is lower.

This is the east side of my office. I'm not quite sure how they decide which wall to do next. I think they decide on the size and time of day?...(if they can finish the wall before they go home.)

This is the storage room. looking out to the 2 doorways.

same wall...again. I don't know why there are 2 light outlets here....there's only suppose to be one. the higher one. I don't know what the lower one is for.

The staircase. I thought they had to finish a wall all in one shot...but maybe they don't?

I, on the other hand, finally finished the first floor. I even did the underside of the doorways. I think they will send me onto the 2nd floor...Not sure...

I need proper scaffolding to do up there...but the guys are using it...and even still, I can't set it up alone. I might ask them to set it up for me one friday before they go home so i can do it on the weekend?


since today was the first time I did the underside of the doorways it was kind of a messy day.