Day 69: backup plan
- Eva Hu
- May 10, 2016
- 2 min read

Today they started on the work that will keep them busy while they wait for the cement to come next week.
These are the skinny blocks for the diving walls between the change room/bathroom in the dance studio.

And here is the wall. They only build half of it so that the cement can dry properly before they raise the wall any higher. Or else, it might topple over.

This is the inside of the wall.

This is the second of only 2 divider walls in the entire structure. It's the wall between the bathroom and the tool room in the workshop.

The lighting isn't so good here but the wall here on the right will make up part of the bathroom and the tool room.

And here's the wall. The wall won't go all the way up. The bathrooms will only have a ceiling of 2.60m. (something like that) and the rest of the space will be open and used as open storage.
Below is the bathroom side of the wall.

This wall is the tool room side of the wall. You can access the storage area above the bathroom here.

While the guys did the brick walls. Luis did the stairs. It was a lot of measuring. planning and drawing.

Luis said it's Joses job to draw out the stairs but then Jose said he only does it for contractors when he knows that the contractor can't do it. He says most people can't do it, so to save time and trouble...he draws it for them. But Luis did it on his own. It was a lot of planning. He started drawing it all Last week or maybe even 2 weeks ago.

Here's what he finished at the end of the day. Soon I won't have to keep asking them if I can go up the ladder. I can mosey up the stairs all on my own! Can't wait. I bet they will feel better too because I will stop bothering them about climbing the ladder.

This space below will be open space in the storage room.

This space below will be a cupboard to store my cleaning supplies.

I wonder if you can walk up all the way to the top yet.

This is the top of the stairs looking up.