Today the guys finished part of the walls upstairs and then started taking down the supports which were holding up the roof. the cement is 300 grade which means it can withstand 300kg per cubic cm. That's crazy! The issue with watering the cement as it cures is also a thing of the past. Luis said there is a special chemical that they mix in the cement so that it dries faster and with no cracks. As the guys were taking down the wooden frames, Luis was checking to see if there was any exposed steel. and He said so far so good. everything came out perfect. Guzman seemed a little offended that Luis doubted his 'perfect' work ;)

Hoy los chicos han quitado todo los puntales. Luis estaba buscando si podia ver acero fuera del hormigón. pero nada. ha dicho que el techo queda perfecto.

A bajo, el oficina

Below is the ceiling of the office.

el oficina

Office again

A bajo, el bano

Bathroom

the guest bedroom

el dormitorio

​The supports that worked hard for the last few weeks. They definitely take a lot of abuse.

Los puntales que han trabajado mucho los ultimas semanas

Here's a video of the guys taking down the supports

Un video quitando los puntales y la madera

The wall separating the workshop bathroom from the dance studio.

El pared que separa el taller del estudio de baile.

The main entrance.

La entrada.

This tiny area is turing out to be quite complicated. I didn't see what happened, but I heard a lot of screaming. I think Guzman got hit by the falling wood when he was pulling it down.

Donde va a ser los escaleras. Ese lugar parece un poco complicado. No vi que ha pasado. Pero escuche gritando... :( Espero que no era demasiado grave.